Rebates Processs in SAP is divided into three components
1) Configuring Rebates
2) Setting Up Rebates
3) Managing rebate agreeeements and payments

Pre-requsiistes- Check the following:

1.The payer partner needs toi have the rebate field checked in the customer master on the sales area-billing doc tab.
2.The Billing type must be marked as relevant for rebates.
3.The Sales Organisation must be marked as relevant for rebates.

Condition Technique :
Rebates, use the condition technique, but distinguish themselves from pricing in applying to transactions over time, versus on a transaction basis. Rebates have their wn field catalog and their own condition table naming convention.So you could have two condition table "001" one for pricing and one for rebates, which could have different key fields. You need to use the technical names A001 For pricing and KOTe001 for rebates when you use the query type using transaction SE 16..
Use create access sequence (AS). Enter 1 in field category for rebate specific. AS after going thru the right path of maintaining access sequence for rebates.
The big difference between the rebate and the pricing access sequence is that there is no exclsuion flag available for rebate related AS. This means multiple tables for an access sequence can be aplied at the same time.
Rebate related condition types are identified by codnition class -C.
After defining and creating condition types for rebated include them in the pricing proceedure. The requirement should be 24 here which implies that the accruals are calculated on the basis of invoice/bill.
The other fields- alctyp and altcbv does not allow you to manipulate how a rebate is calculated. Also, remove the requiremnt 24, if u want to see reabtes at order time.

Now payment of rebates:
Payments can be maunal or in full settlement. When you do manual payments, it defines how much can be paid out during a partial settlemetn. You use partial settlement only when rebate agreement is defined for a full year but the paoyouts are supposed to happen on a monthly, quarterly or anyother specified period.
These accurals are based on sales volume and when they are posted billing is created int eh follwoing manner. Provision for accruals is debited and Sales revenue is credited. When rebate credit memo is created
Customer account/ is debited and
Accrual provision account is credited.
Also, please note that when rebates are created without dependent ona material but on customer/material you need to refer to a material for settlement.

What exactly do you wish to know in Rebates? The total outline of the Rebate process or each and every step in the SAP system?
First of all rebates are more or less discounts which are offered to customers. The rebates are based on the volume of the business the customer does with you within a specified time. for eg if the customer agrees for Rs.1 Crore worth of business with u in 1 year, then you activate your rebate porocess. if at the end of the year the customer DOES achieve the target u offer him say 2/3/4 % whatever is decided. The rebates are passed on to the customer in the form of Credit notes.
The rebate can be given to the customer at one time or in installments also.
This is broadly the outline of the rebate process.

Note : I recomend you to study the theory part of why rebate and why not a discount.
This will help you understand better.
May be I can help you with rebate process.(IN -IMG)
1. define a rebate agreement type
2. define a condition type group
3. define a condition type and place this condition
Type in the pricing procedure.(REQUIREMENT=24)
ALSO IN THE PROCEDURE- ACCRUAL KEY = ERU
YOU ALSO HAVE TO DO THE ACCOUNT DETERMINATION FOR REBATES.
Once you have defined all the 3 and assignment starts.
Assign the agreement type to the condition type group
Assign the cond type group to the condition type.

Condition technique is also used in rebates.
REBATE ACTIVATION- IN CUSTOMER MASTER, SALES ORGANISATION AND FOR THE BILLING DOCUMENT.
After having done this please proceed to maintain the condition record for the rebates (transaction code-vbo1)
Note: if you maintain the requirement coloumn with the requirement as 24 - the rebate will be affected in the billing document and if you dont give the requirement as 24 your rebate will be affected in the sales order.
The rebate process is completed when you have created a credit memo to the customer.
The document type for the partial settlement is R3.
Please make sure you open two screens SO THAT YOU CAN COMPARE THE NEW ENTRIES WHAT EVER YOU'RE DEFINING WITH THAT OF THE STANDARDS or first you try with the standard condition type boo1, boo2
boo3 boo4.
AFTER YOU HAVE FINISHED A COMPLETE SALES CYCLE OF CREATION ORDER , DELIVERY AND BILLING.
GO TO THE CONDITION RECORD IN CHANGE MODE (VB02) AND SETTLE THE ACCOUNT PARTIALLY.
I hope this will be of any help to you.

In a simple way,
1. First you need to create a Rebate agreement.
2. Create condition record for rebate giving the rebate rate and accrual rate.
3. when the rebate relevent billing doc is generated, the rebate and accruals are determined and posted in a seperate GL account as a noted item - amount to be settled. Also it gets copied in the rebate agreement.
4. create settlement run using credit memo request and then credit memo to settle this amount with the customer.



posted by syed zabee


Rebate Process with Ref. to Sales Order


If I need to make a rebate for a customer what is the process involved.
I am providing some info on rebates which I know.
Rebate agreemnts is based on agreement types.Conditon records which are created like B001 and B002 are linked to the rebate agreeements specifying the rebate rate + the accrual rates.condition records specify the rebate rate and the accrual rates.
Consider an example..
You decided to give a rebate of 3% to a customer whose sales vol is $1000 for a particular SO
Then the rebate value is $30..
Now when you make the rebate settlement by doiing the Credit memo and you decide to pay $27, then the accounting will be generated saying 27$ paid towards rebate and 3$ is the accrual which you owe to the customer
Procedure:

Rebate agreement: Transaction code: VB01
When you go to VB01, choose agreement type 0002 and then in conditions give
Material rebate
1 20
20 30
Now create a sales order with a material say M-11 for SOrg 1000 12 00 with QTY 6
Now check VB03 and see rebate agreemtent it will say Accruals 120 and payments 0
since your rebate is not settled still.

Rebate setllement 

Go to VB02 enter ur sales deal no, and change the agreemetn status to B then enter Shift+F12 and enter the amount to be paid for example u say $80
Then check in rebate payments rebate doc and partial setllemetn since you have not paid in full.
View the credit memo request
Remove the Billing bloock Go to VA01 and put order type G2 ,,,go to create with ref and enter ur Sales order no,,,save the doc now...
Then go to VF01 and enter the credit memo reqst no generated...save the doc no and go to VF02 and say release to accounting
Now the final settlement will be this way
Accruals:120
Accrual reversed:80
Rebate pay:80
Amount payable:40
So the balance 40 is still the accrual
This is an example how a rebate will be processed with ref to a SO with an example.

How to do a rebate agreement for a specific customers with settings details?

1. Create a condition by copying a a standard condition like BO03 in V/06
2. Assign this condition in the std pricing procedure with acct key as ERB and accural key as ERU - V/08
3.Create a Rebate Agreement in VBO1 (It is O = Owl and not zero). No will be generated
choose 003 - Customer rebates, enter the customer code, the validity and check for the status shld be in Open, click on the conditions enter the percentage and accrual amount. You also can have scales in this. Also you need to maintain the material for the settlement
4. Create a sales order for that customer and check the rebate agreement.
5. You can see the rebate condition in the invoice only.
6. Once you have posted the invoices, then go to rebate agrrement no. clicl on verficayion and it will show the order details.
7. For settlement change the status of the rebate to B - release for the settlement.
8. Credit memo request will b generated copy the no. and go to VA02, remove the blocks if any and create an invoice (credit memo).this will show u the accrual amount.
9. In both the invoice and the credit memo check the posting - accounting document it will show u the accrual as negative.
10. Again go to rebate aggreement and check the status it will show you D - Final settlement of agreement already carried out